The following projects were submitted to Engineers Australia. The purpose was to demonstrate my competency as an Electrical Engineer, at a professional engineering level. The Competency Demonstration Reports are  combination of my academic projects and work experience (internships). I was recognised as a Professional Electrical Engineer Level 1 by the institute of Engineers Australia based on my work experiences and University Projects.

Projects
tl.jpg

Electrical Engineer Intern                                                    12th Oct. 2013 – 25th Apr. 2014

Ankhu Khola Jalbidhyut Company LTD.

Naxal-1, Kathmandu Nepal

​

Core Responsibilities:

​

  • Operation of 8.4MW Power Plant.

  • Generating Hydro Power of 8.4MW and Transmitting (33KV) to Grid.

  • Repair and Maintenance of Power Plant, 4 Substations under the Powerhouse and 33KV Transmission line.

  • Improvement of Plant Capacity factor by working on team to define the operation strategies.

  • Controlling and monitoring of Power Plant using Supervisory Control and Data Acquisition (SCADA).

  • Cost calculation of total Power (Megawatts) per months transmitted to Grid.

  • Troubleshooting of LV (415V, 6.6KV) and MV (33KV) Panels.

  • Manage team to complete internal projects such as Evacuation Pump overhauling, Cooling system overhauling, Turbine Overhauling.

  • Reporting and Documentation.

​

Additional Responsibilities:

​

  • Team (technicians) management role, to ensure completion of internal projects

  • Attending and participating in team meetings

  • Ensuring compliance with National, Organisational and Engineering standard operating procedures, policies and best practices

  • Reporting & Documentation

​

Hierarchy 

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

1_edited.jpg
Image by Jonathan

Network Technical Specialist                                            28th Nov. 2017 – 15th Feb. 2018

(Level 1 & 2/ Internship)     

Westcon-Comstor Australia

Unit 4, 39 Herbert Street St. Leonard NSW 2065 AUSTRALIA

​

Core Responsibilities:

​

  • To perform Level 1, 2, and 3 operations on Cisco Networking Devices (Routers, Switches, Access Points etc.)

  • To manage the day to day flow of orders through the Integration Centre.

  • Oversee the staging of hardware from manufacturers in the Westcon-Comstor vendor portfolio (Mainly Cisco Systems).

  • Ensure all kit builds are completed as per the specified order.

  • Creating and updating of Technical documents (project diagrams, configurations, and guides).

  • Work with the Services to manage the staging of projects.

  • To maintain understanding of Westcon-Comstor technical offerings.

  • Keep records of customer interactions and transactions, recording details of inquiries, complaints, and comments, as well as actions taken.

  • Continual updating of technical skills.

  • Workplace continuous improvement: tools, facilities, software, and process.

 

Secondary Responsibilities:

 

  • To configure hardware from manufacturers in the Westcon-Comstor vendor portfolio.

  • To install hardware and software/IOS into all vendors’ kit. (CISCO Networking Devices).

  • Ensure all kit builds are completed as per the specified order.

  • Install and perform minor repairs to hardware, software, and peripheral equipment, following design or installation specifications.

  • Read technical manuals, confer with users, and conduct computer diagnostics to investigate and resolve problems.

  • To proactively follow up on customer order inquiries.

  • Create and modify SharePoint Logistics page as required (RMA, refurb and calendar lists).

5_edited.jpg

Integration of Renewable Energy Power Generation with Voltage Source Converter (VSC) Inverter Connected Load.  

​

Objectives:

​

Project aims and objectives included,

  • Renewable Energy power generation

  • Design & Development of VSC which has grid integration capabilities

  • Implementation of the black-start capability of VSC

  • Practical testing and implementation of VSC for energy conversion to AC power for 50/60Hz frequency

  • Reduction of harmonics

​

Tasks :

​

  • Literature review of different converters (Each member focused on one type. My focus area was buck-boost and Cuk converters)

  • In-depth study of VSC – Topologies, Design and mathematical modelling

  • Study of Black-start VSC

  • Responsible for providing the technical requirements for a Black-start service

  • Running simulations for RL load (Team members worked on Resistive load)

  • Design of the logic circuit

  • Provide help with the switching & SMPS circuits to team members

  • Hardware implementation and integration of all circuit modules

  • Running final tests and recording results

  • ​

Managerial Duties:

​

I had the following project management related duties,

  • Creating the initial project plan

  • Develop the work breakdown structure and schedule tasks & activities

  • Task delegation

  • Monitoring project progress

  • Team management such as conflict resolution

​

VSC Design

​

​

​

​

​

​

​

​

​

​

​

​

​

​

System Model

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

Implementation

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

Results & Outcome

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

2_edited.jpg
3_edited.jpg
4_edited.jpg
5_edited.jpg
8_edited.jpg

Grid Integration of Renewable Energy Using Pulse Width Modulation (PMW) Inverter

​

Objectives:

​

This project was a somewhat extension to the VSC converter project. Previously, we converted the variable DC from the renewable source into fixed DC. Here, we had to implement the 3-phase PWM inverter in association with IGBT, to get a AC power and then integrate it to the grid via a synchronizer. Salient points of include,

  • Implementation of the PWM inverter

  • To have grid integration capabilities

  • Inclusion of microcontroller for IGBTs conduction

  • Determining circuit’s zero crossing

  • Synchronization of the AC output power with the grid

  • Final grid integration & testing

​

Tasks :

​​

  • Background knowledge & Literature Review

  • Running MATLAB simulations for Buck-Boost & Cuk Converter

  • MATLAB Simulations for Full bridge VSI

  • Sinusoidal PWM inverter design, mathematical modelling & simulations

  • Circuit design & implementation of SPWM inverter, driver IC and Pulse amplification unit

  • Collaborating with hardware implementation of the project

  • Final integration & testing

​

Managerial Duties:

​

I had the following project management related duties,

  • Creating the initial project plan

  • Develop the work breakdown structure and schedule tasks & activities

  • Task delegation

  • Monitoring project progress

  • Team management such as conflict resolution

​

Circuit Design

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

 

 

 

 

 

 

 

 

 

 

 

 

Hardware Results

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

 

 

 

​

​

​

Results & Outcome

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

6_edited.jpg
Testimonials
 
​“Comprehensive, theory-based understanding of the underpinning natural and physical sciences and the engineering fundamentals applicable to the engineering discipline.”
 

Afsar Ali SHAIKH, Electrical Engineer

Testimonials
​
“Application of established engineering methods to complex engineering problem solving.”
​